Monday, September 26, 2005

Lake/Dam News from NE WI

Dunn County News

Draw down and out
By Joel Becker, Editor

On Friday, the draw down of Tainter Lake reached the five-and-a-half-foot mark. The level of the lake was taken down so that work can be done to the dam in Cedar Falls by Xcel Energy.

According to Rob Olson, hydro licensing specialist with Excel based in the Western Avenue Service Center in Eau Claire, the draw down went well.

He reported that earlier in the week he accompanied DNR officials to check on areas where fish may be stranded by the dropping level of the water. "We didn't find any problems at all," he said.

The lake was taken down in six-inch-per-day increments, which Olson said allowed fish to escape to deeper water.

While much of the lake and river area behind the dam just looked like there was much less water available, the area near Champney Park showed what people have known for years.

There is a large amount of sediment on the north end of the lake where the Red Cedar River feeds into the larger body of water.

Though Excel has nothing to do with the sediment, Olson's observation was, "You get a really good appreciation for the amount of sediment that has been delivered to that lake since 1910. God knows how many truckloads of sand you'd have to haul out of there to restore it."

At the dam, subcontractors have begun working to replace the old wood flashboards. During the next four to six weeks the level will be kept down and the concrete on the dam will be prepared for the new rubber system.

Olson said he believes the flashboard system was installed in the 1930s following a flood. He also said the flashboards allowed more energy to be generated, but during high-water events the flashboard would sometimes get washed out.

Once the water level went down, the flashboards would have to be replaced.

"We knew this project was upcoming and it was just a matter of time of getting the new license to where we could ahead and start the project," Olson said. "We've just gotten by with the basic essentials knowing we were going to replace them anyway."

He said the rubber system doesn't give any more spillway capacity, but the level of the lake will be able to be controlled better.

In the past, when the boards went out, Olson said there would be a four-foot draw down to replace the boards, which happened, on average, once a year. The repair and replacement of the boards cost about $10,000 per time.

"People have this idea that the flashboard didn't work very well," Olson said. "That's exactly how flashboards work. That's how they're designed. They're designed to fail and they're designed to fail to pass excess water that you can't pass any other way. They've actually been very effective for a lot of years. Now we're just going to a new system where we won't have the draw down anymore."

The cost of the project is $600,000.

If everything goes well, Olson estimates that by the end of October or the first part of November, the lake will be back up to its usual level.

However, heavy rains and increased flow in the river in the next four to six weeks could delay the project.

The lake will be refilled at a 60/40 rate.

Olson said 60 percent of the water that flows through the river will be passed downstream and 40 percent will be retained to fill the lake.

"We could fill it a lot quicker, but we don't want to cut off flow because eventually there's no water downstream," he said.

Thursday, September 15, 2005

Update on NR 326 Pier Rules

September 15, 2005
In response to the 300-plus public comments received, DNR's habitat protection staff developed a final proposal for revisions to NR 326 - the state's pier rules. This proposal will be considered for adoption by the Natural Resources Board at their September 28 meeting. The final proposal for revisions to NR 326 achieves the 2004 law's aim to provide clear simple requirements for waterfront owners to place piers in aid of navigation, while protecting critical fish habitat and assuring each citizen's right to boat, fish and enjoy other recreation in Wisconsin's public waters.

Most piers will be exempt

Under the proposed rules, the most of the nearly 500,000 existing piers in Wisconsin will continue to be exempt from permitting, as has been the case under guidelines in effect since the early 1990s. New piers can also be placed in any waterway without a permit unless they're proposed to be located in "sensitive areas," that have been formally designated on a very small number of lakes (138 currently). To be exempt, property owners simply need to follow the size limits established by the law, along with a few other common-sense requirements. Piers that already have a permit are not affected by the proposal

Virtually all larger piers will be grandfathered, only largest require detailed review

Most non-exempt larger piers will be "grandfathered" through a one-time, $50 "general permit" that allows owners to keep what they have, with a few limitations. Five other categories of general permits are created for specific piers or boat shelters that aren't exempt. Larger piers not qualifying for any of these categories -- less than one-half of 1 percent of all piers -- will need to get a more detailed individual permit with a more comprehensive review. These very large structures have the greatest potential to harm fish habitat and interfere with boating, swimming and other recreation in public waters.

Factsheet and documents available

Attached is a Factsheet that explains the NR 326 proposal. You can also go to DNR's web page at the link below, to find more information and links to other rule-related documents.

DNR Pier Rules

A $200,000 Windfall for DNR Projects

How did Jefferson County find the money for a fish ladder currently being constructed at the dam in Jefferson?
Dan

The old-fashion way, through a lawsuit settlement

Neighbors Standing United (NSU) and the Wisconsin Wetland Association (WWA) requested a contested case hearing regarding issuance of DNR permits for a gas pipeline; believing that the permits were inadequate to protect the affected wetlands and aquatic systems.

Below is a summary of the violations and the settlement that Attorney General Peg Lautenschalger's Dept. of Justice reached with Guardian Pipeline:

Guardian Pipeline Permit Violations

· Deposition of sediment in wetlands crossed by the pipeline
· Deposition of sediment in wetlands adjacent to the right of way
· Failure to erect erosion control fences
· Unnecessary and uncontrolled erosion
· Unapproved grading on the banks of navigable waters
· Improper and erroneous delineation of wetlands
· Incorrect translation of delineated wetland boundaries to actual field marking
· Failure to wash vehicles to prevent the spread of non-native species, which is a form of environmental pollution
· Failure to maintain erosion control best management practices
· Erosion of soil stockpiles
· Diversion of water from streams
· Failure to place and use timber riprap mats
· Placement of trench spoils on top of erosion control devices
· Placement of trench spoils outside of designated rights-of-way
· Use of over ground-weight construction equipment, resulting in permanent damage to wetlands
· Failure to maintain erosion control in a timely manner following storm events

Allocation of Guardian Pipeline Settlement Funds

· $17,000 towards installation of a fish ladder on the Jefferson Dam on the Rock River
· $25,000 to the Jefferson County Land Trust for acquisition of property, easements and development rights for wetland preservation in the area of the pipeline
· $20,000 to the University of Wisconsin (through UW Extension) for a well-designed wetland restoration project in the pipeline area in Jefferson County, led by Professor Joy Zedler
· $38,000 to Pheasants Forever and the Audubon Society for a large (2700 acres together with a companion 1700 acres nearby) wetland restoration project called the Jefferson Marsh.

In addition, the DNR has agreed to provide WWA and the property owners additional input into wetland restoration issues, and has agreed to a number of provisions which we believe will improve the prospects for restoration of more of the wetlands impacted by the Guardian Pipeline project.

Rock River Coalition Supporters

Brian;
Who is the Rock River Coalition, and can they be enlisted for support by our lake district?
Jim
The Rock River Coalition is a group that probably opposes most of what the RKLD is trying to accomplish. They were formed in 1994 and are a non-profit that requires dues for membership.

From RRC's website:
In mid 1998, the Department of Natural Resources (DNR) approached the RRC to become its basin-wide partnership group.
Their donor and membership list includes;

Ken Johnson, DNR
Mr. Johnson has been the leading voice opposing a water level increase on Lake Koshkonong;

Todd Ambs, DNR
Mr. Ambs is formerly of the WI River Alliance, a leading advocate of Dam removal throughtout WI;

Suzanne Wade, UW-Extension
Ms. Wade served as moderator of the February, 2003 Facilitated Meeting required by the DNR;

Tom & Lois Shearer, Lake Koshkonong Wetland Association members
Gary & Penny Shackelford, Lake Koshkonong Wetland Association members

RRC received their largest donations from the DNR, and, as a party to the Guardian Pipeline Settlement, received a portion of the $100,000 Guardian paid to Jefferson County.

Wednesday, September 07, 2005

Rock River Coalition Award

Tom Presny Honored with the 2005 Rock River Basin Friends Award,

Tom Presny, Janesville’s Park Director, recently received the Rock River Basin Friends Award for 2005. This award is given each year by the Rock River Coalition, Inc. to a volunteer for his or her work to protect the Rock River Basin.

The Rock River Coalition is a non-profit organization that works to improve the environmental, recreational, cultural and economic resources of the Rock River Basin. Tom has been a long-term volunteer with the Rock River Coalition Board of Directors and served on its Recreation Issues Team where he was an advocate of improving recreational opportunities along the Rock River.

As Leisure Services Director Mike Williams explains, “Tom has volunteered with the Rock River Coalition for quite some time and this award further exemplifies his dedication to Wisconsin’s natural resources and his commitment to educate the public about the unique qualities of the Rock River watershed. I applaud Tom’s efforts and congratulate him on this award.”

Tuesday, September 06, 2005

Water Level Update

Today's water level stands at 776.08, or a quarter inch BELOW our summer minimum level of 776.10.

Or, put another way, we are 3.5 inches ABOVE our winter maximum level.

(see comparison graph)

The winter orders go into effect November 1st.

September Meeting Notice

The RKLD Board of Commissioners will meet on Tuesday, September 13th, at 6:30pm, at our usual location.

Please see the meeting info page for the agenda.