Monday, March 11, 2013

Dredging Update 3-11-13


Construction is nearly complete with only punch list items outstanding.
·         The silt logs have been pinned to the berm for temporary stabilization and the silt curtain has been removed.
·         Remaining work includes completing the carp gate anchorage work (being performed while on site), setting the final placement of the rock at the back of the dredge placement area (being performed later that day), finishing the boat launch grading (being performed later that day), applying the polymer, removing the tubing used for artesian well control, cleaning up the staging area and removing the snow fence, and removing the traffic controls when snowmobile traffic is no longer a concern.
·         With only wrap up items remaining, the site will be inspected on a three-week basis until permanent stabilization has occurred.