  • The survey staking has been completed and the benchmarks have been placed, and Badgerland is preparing the site for construction. They are hoping to start active construction on Thursday. 

  • Public notice fliers have been distributed along Lamp and North Shore Roads, as well as at the Sunset Bar and Grill, and the Town of Sumner Town Hall. 

  • Pre-construction road inspection has occurred, and Badgerland has opted to stay below the weight limit in Sumner, and they will be getting a permit from the Town of Koshkonong. 

  • As we talked about earlier, the Sunset Bar and Grill will be directing motorcyclists to access the lake at two other locations and will keep their activities away from the construction site. 

  • A construction kickoff meeting happened this Monday at the boat launch: Travis Schroeder from the DNR, Ricky from GLARC, Rick Gerke, Tim and Kevin from Badgerland, and myself and Rob were present. We had a couple loose ends to tie up, but it seems like given good weather, we should be good to go on the project. I'll be issuing the full minutes from the meeting later today.