Lake Koshkonong Erosion Control (UPDATE)


Hi all,
 
Please find attached the weekly erosion control inspection for the Lake Koshkonong Dredging and Shoreline Restoration Project conducted on 02/11/2013. Below are the items of note:
 
  • Active construction of the berm began on 02/11/2013, and is proceeding well.
  • All erosion control measures in place and appear to be functioning appropriately, including the tracking pad and the silt curtain.
  • Silt sock has not yet been placed, as the ice in the shallower areas has not yet been removed. Badgerland will place when appropriate.
  • I will be leaving a copy of the inspection with Kevin while on site today to add to the on-site file.