Diggin' in: Dredging of Lake Leota begins
Janesville Gazette
BY THE NUMBERS
24
Hours a day two crews are working
6,000
Cubic yards of material taken from lake per 12-hour shift
200,000
Cubic yards of material to be removed by completion
20
Cubic yards carried in an off-road truck per load
60
Loads each truck carries in a 12-hour shift
130,000
Pounds a loaded truck weighs
80
Acres on which the dredged material is being spread
$3,480
Cost of diesel fuel used by equipment every 12-hour shift
$1.37 million
Amount city borrowed for the project
$30
Cost of the project this year for a taxpayer with a $100,000 home
$885,069
Integrity's winning bid